Die FBB betreibt den Flughafen Schönefeld und über ihre Tochtergesellschaft BFG den Flughafen Tegel. Im Jahr 2017 wurden an den Flughäfen rund 33,3 Millionen Passagiere befördert. Damit ist Berlin der drittgrößte Flughafenstandort in Deutschland. Um die nötigen Kapazitäten für die Zukunft zu schaffen, entsteht derzeit der neue Flughafen Berlin Brandenburg Willy Brandt am Standort Schönefeld.
Aufrufe
vor 1 Jahr

Annual Report 2015

  • Text
  • Berlin
  • Aircraft
  • Brandenburg
  • Assets
  • Flughafen
  • Tegel
  • Passengers
  • Terminal
  • Previous
  • Consolidated
Portraits, finances, prospects: Flughafen Berlin Brandenburg GmbH presents its key business segments, latest financial statements and most recent developments in the annual report.

→ 26 | Flughafen

→ 26 | Flughafen Berlin Brandenburg GmbH Berlin Brandenburg Airport How Is the Construction Work Processing? year; the most important reasons were related to the bankruptcy of an important construction service provider and more extensive planning. FBB subsequently revised parts of the schedule and initiated acceleration measures. They are aimed at further optimisation of the processes in the areas approval, planning, construction and technical operational startup. In addition, the processes for the technical startup are to be more tightly meshed with the operational startup. Progress at the construction site can be tracked on the monthly BER Barometer. The Barometer is published on the road map: http://ber.berlin-airport.de. ← Picture pages 24/25: View of the BER terminal from Airport City. FBB presented the time schedule for the completion of construction and operational startup of BER in December 2014. It sets the second half of 2017 as the target date for the opening of BER. While all of the planned milestones were achieved at the beginning of 2015, delays in the completion of the construction of three to four months became apparent in the middle of the Achieved milestones The overhaul of the main duct in the terminal was completed in 2015 and the first months of 2016, the work on the cable boxes was completed for the most part and all seven segments of the primary smoke removal control system were completed. Parallel to these activities, a major part of the areas that had not yet been properly connected were incorporated into the smoke removal systems and the fresh air flow in 2015. Moreover, solutions were found for all of the construction

News from BER | 27 ← Schulzendorfer Elektro is installing the cables for smoke windows in the Main Pier. Low-voltage power lines are connected for a segment of the GSPLCs. defects and the outstanding work, and the points will now be successively completed. The construction of the pavilions next to the passenger terminal was also completed. Planning The fifth and sixth addenda to the construction permit were submitted to the Building Authority in 2015; the aim of this work is to secure the future capability of the passenger terminal to handle traffic. In February 2016, the Airport Company submitted the missing documents for the 5th addendum and is currently working on the later requests from the Building Authority. The construction of the terminal cannot be completed until all the permits have been issued. The third addendum to the construction permit for the South Pier has been approved by the Building Authority. Technical startup The technical startup of the equipment and systems installed in BER will begin parallel to the completion of construction. The teams began their activities in 2015 and are currently working on a series of systems in the passenger terminal. For example, mechanical ventilation systems, smoke removal systems or electrically controlled doors are already in operation in the Main Pier North. The technical startup is split into three phases. During the first phase, all of Two engineers from the company Käfer during the documentation and testing of the installed fire protection bulkheads. the systems will be started up individually by the installation companies. During the second phase, the interfaces between the systems will be tested and hot gas smoke trials will be conducted. During the third phase, the general assessor will test and examine the individual systems as well as the operation of the overall complex of systems.

Unsere Publikationen

Annual report 2016
Geschäftsbericht 2016
Annual Report 2015
Geschäftsbericht 2015
Geschäftsbericht 2014
Geschäftsbericht 2013
Annual Report 2012
Geschäftsbericht 2012
Geschäftsbericht 2011
Geschäftsbericht 2010
Annual Report 2009
Wegweiser Flughafen Tegel
Wegweiser Flughafen Schönefeld
Flugplan Sommer 2015 SXF/TXL Timetable Summer 2015
Flugplan Winter 2014/2015 SXF/TXL - Update
Flugplan Winter 2014/2015 SXF/TXL
Flugplan Sommer 2014 SXF/TXL
Flugplan Sommer 2014 SXF/TXL
BER aktuell 04/2018
BER aktuell 02/2018
BER aktuell 01/2018
BER aktuell 12/2017
BER aktuell 11/2017
BER aktuell 10/2017
BER aktuell 09/2017
BER aktuell 08/2017
Fluglärmbericht 2016
BER aktuell 07/2017
BER-aktuell 01/2017
BER aktuell 12/2016
BER aktuell 11/2016
BER aktuell 10/2016
BER aktuell 09/2016
BER aktuell 08/2016
BER aktuell 07/2016
Schallschutzfibel
BER aktuell 06/2016
Fluglärmbericht 2015
BER aktuell 03/2016
BER aktuell 01/2016
BER aktuell 12/2015
BER aktuell 11/2015
BER aktuell 10/2015
BER aktuell 09/2015
BER aktuell 08/2015
BER aktuell 07/2015
Fluglärmbericht 2014
BER aktuell 06/2015
BER aktuell 05/2015
BER aktuell 04/2015
BER aktuell 03/2015
BER aktuell 02/2015
BER aktuell 01/2015
BER aktuell 12/2014
BER aktuell 11/2014
BER aktuell 10/2014
BER aktuell 09/2014
BER AKTUELL 08/2014
BER aktuell 07/2014
BER aktuell 06/2014
BER aktuell 01/2014
BER aktuell 05/2014
BER aktuell 04/2014
BER aktuell 03/2014
BER aktuell 02/2014
BER aktuell 12/2013
BER aktuell 11/2013
BER aktuell 10/2013
BER aktuell 09/2013
Umweltbericht 2016
Fluglärmbericht 2016
Umweltbericht 2014
Fluglärmbericht 2014
Fluglärmbericht 2013
Umweltbericht 2012
Fluglärmbericht 2012
Umweltbericht 2011
Gate 66 Frühjahr 2012
Gate 70 Sommer 2013
Gate 67 Herbst 2012
Gate 68 Winter 2012
Gate 69 Frühjahr 2013
Berlin Aircraft Brandenburg Assets Flughafen Tegel Passengers Terminal Previous Consolidated

News